Consultancy Services for Preparation of Feasibility-Cum-Preliminary Design for 4/6-laning of Selected Stretches of N.H to be executed as BOT(Toll) Project on DBFO Pattern under NHDP Phase III” (Group – C, Package No. NHAI/BOTII/DPR/09) Jhansi-Khajuraho, NH-75in State of UP&MP of 172 Km
The total length of this Jhansi-Khajuraho, NH-75 Section BOT Project is 172 K.M. The Government of India has taken up an ambitious programme of widening the existing two lanes of the National Highways falling along the alignment of the four /six lanes. As part of this programme, four laning of National Highway-75 between Jhansi-Khajuraho. A portion of NH-75 which passes through UP and MP. The National Highways Authority of India with possible funding from BOT Basis and decided to improve this section of National Highway to International standards and thereafter operate and maintain the highway under a suitable concession agreement.
Details of Bridges:
(3 Major Bridges, 35 Minor Bridges and 221 Culverts)
1 |
Ch. 13+100 |
18 x 30
2 x 11.4 |
Major Stone Arch Bridge |
2 |
Ch. 68+100 |
9 x 15.0 |
Major Arch Bridge |
3 |
Ch. 82+000 |
27 x 28.30 |
Major Arch Bridge |
|